SSC CGL / CHSL Strategy: Time & Work (including Pipes & Cisterns) contributes 2 questions in SSC CGL/CHSL Tier-1 and 2-3 in Tier-2. The LCM (Total Work) method, MDH formula, alternate-day cycles, and efficiency-ratio wages are the highest-yield techniques.
Core Concepts & Exam Coverage
The LCM Method & Efficiency
Instead of using 1/A + 1/B fractions, assume Total Work = LCM of all given days. Efficiency = Total Work / Days.
Time = Total Work / Efficiency; Efficiency is inversely proportional to Time.
Wages are ALWAYS distributed in the ratio of work done (or Efficiency, if everyone works for the same number of days).
Leaving before completion: If A leaves x days before completion, ADD A's x-day work to Total Work and divide by (A + B)!
MDH Formula & Alternate Days
When men, days, hours, and work vary together, use the universal Chain Rule (MDH).
Alternate Days: Compute 2-day (or 3-day) cycle work, scale up close to Total Work, and handle the final partial cycle carefully.
Negative Work (Leakage/Emptying Pipe): Assign negative efficiency to outlet pipes.
AND / OR Group Problems & Contractor Tricks
SSC frequently asks 'a Men OR b Women' vs 'a Men AND b Women' problems.
If M1 men OR W1 women do a job in D days: (M2/M1 + W2/W1) * Required_Days = D.
If A+B take x days more than A alone and B alone takes y days more than A+B: Time(A+B) = sqrt(x * y).
SSC CGL / CHSL • Mathematics
Time, Work & Pipes
Solved PYQs, Traps & Step-by-Step Explanations
Previous Year Questions & Solved Examples
SSC CGL / CHSL PYQQ1. SSC CGL: A can do a work in 12 days and B in 15 days. They work together for 4 days, then A leaves. In how many more days will B finish the remaining work?
Total Work = LCM(12, 15) = 60. Eff(A)=5, Eff(B)=4. 4 days work = 4*(5+4) = 36. Remaining = 24. B takes 24/4 = 6 days.
SSC CGL / CHSL PYQQ2. SSC CHSL: 15 men working 8 hours a day complete a task in 10 days. How many men are needed to complete it in 12 days working 5 hours a day?
SSC CGL / CHSL PYQQ3. SSC CGL: A alone takes 8 hours more than A+B together, and B alone takes 4.5 hours more than A+B together. How long do A+B take together?
Time(A+B) = sqrt(8 * 4.5) = sqrt(36) = 6 hours.
SSC CGL / CHSL PYQQ4. SSC CGL: Pipe A fills a tank in 20 min, Pipe B in 30 min, and Pipe C empties it in 15 min. If all three are opened together, when will the tank be full?
Q4. A can do a work in 20 days and B in 30 days. They start together, but A leaves 5 days before completion. In how many total days was the work finished?