SSC CGL / CHSL Strategy: Time & Work (including Pipes & Cisterns) contributes 2 questions in SSC CGL/CHSL Tier-1 and 2-3 in Tier-2. The LCM (Total Work) method, MDH formula, alternate-day cycles, and efficiency-ratio wages are the highest-yield techniques.

Core Concepts & Exam Coverage

The LCM Method & Efficiency

Instead of using 1/A + 1/B fractions, assume Total Work = LCM of all given days. Efficiency = Total Work / Days.

  • Time = Total Work / Efficiency; Efficiency is inversely proportional to Time.
  • Wages are ALWAYS distributed in the ratio of work done (or Efficiency, if everyone works for the same number of days).
  • Leaving before completion: If A leaves x days before completion, ADD A's x-day work to Total Work and divide by (A + B)!

MDH Formula & Alternate Days

When men, days, hours, and work vary together, use the universal Chain Rule (MDH).

  • (M1 * D1 * H1 * E1) / W1 = (M2 * D2 * H2 * E2) / W2.
  • Alternate Days: Compute 2-day (or 3-day) cycle work, scale up close to Total Work, and handle the final partial cycle carefully.
  • Negative Work (Leakage/Emptying Pipe): Assign negative efficiency to outlet pipes.

AND / OR Group Problems & Contractor Tricks

SSC frequently asks 'a Men OR b Women' vs 'a Men AND b Women' problems.

  • If M1 men OR W1 women do a job in D days: (M2/M1 + W2/W1) * Required_Days = D.
  • If A+B take x days more than A alone and B alone takes y days more than A+B: Time(A+B) = sqrt(x * y).