UPSC CSE ⏱️ 4 Min Read

Environmental Impact Assessment (EIA) & Parivesh

UPSC CSE • Social Studies

Environmental Impact Assessment (EIA) & Parivesh

Environment — Concept Notes & High-Yield Points

UPSC CSE Strategy: Environmental Impact Assessment (EIA) is a statutory decision-making tool under the Environment (Protection) Act, 1986. UPSC Prelims tests the 4-stage EIA cycle (Screening, Scoping, Public Consultation, Appraisal), Category A vs. Category B projects, and the PARIVESH portal.

Core Concepts & Exam Coverage

Statutory Basis & Evolution of EIA in India

EIA evaluates the likely environmental, social, and health impacts of a proposed project prior to decision-making. In India, it derives statutory force from the Environment (Protection) Act, 1986.

  • 1994 Notification: Made Environmental Clearance (EC) mandatory for specified developmental projects for the first time.
  • 2006 EIA Notification: Currently governing framework; decentralized project appraisal into Category A (Central level) and Category B (State level).
  • PARIVESH (Pro-Active and Responsive facilitation by Interactive, Virtuous and Environmental Single-window Hub): Single-window online portal by MoEFCC for Environment, Forest, Wildlife, and CRZ clearances.
  • Strategic Environmental Assessment (SEA): Evaluates environmental impacts of broader policies, plans, and programmes (unlike project-level EIA).
Project CategoryAppraisal AuthorityEIA Requirement
Category AExpert Appraisal Committee (EAC) at MoEFCC (Central)Mandatory EIA & Public Hearing
Category B1State Expert Appraisal Committee (SEAC) & SEIAAMandatory EIA & Public Hearing
Category B2SEAC / SEIAA (State)Exempt from full EIA & Public Hearing

The Four Stages of EIA Cycle (2006 Notification)

Every non-exempt project must pass through a structured four-stage clearance pipeline before construction or land preparation begins.

  • Stage 1 — Screening (Only for Category B): Determines whether a Category B project requires a full EIA (classified as B1) or not (classified as B2). Category A projects skip screening and mandatorily require EIA.
  • Stage 2 — Scoping: EAC or SEAC determines the Terms of Reference (ToR) specifying all relevant environmental concerns to be addressed in the EIA report.
  • Stage 3 — Public Consultation: Consists of a Public Hearing at the project site (conducted by SPCB) and written responses from stakeholders; B2 projects and certain strategic/linear projects are exempt.
  • Stage 4 — Appraisal: Detailed scrutiny of the final EIA report and public hearing outcomes by EAC/SEAC to recommend grant or rejection of Environmental Clearance.

Social Impact Assessment (SIA), EMP & Coastal Regulation Zone (CRZ)

Modern impact assessment integrates social displacement, mitigation planning, and coastal zoning.

  • Environmental Management Plan (EMP): The action plan detailing mitigation measures, monitoring schedules, and budgetary allocation to offset adverse impacts identified in EIA.
  • Social Impact Assessment (SIA): Mandated under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement (RFCTLARR) Act, 2013 for land acquisition.
  • CRZ Notification, 2019: Classifies coastal areas into CRZ-I (ecologically sensitive: mangroves, corals, turtle nesting), CRZ-II (developed urban areas), CRZ-III (rural areas, split into III-A and III-B based on population density), and CRZ-IV (water area up to 12 nautical miles).